
Important Milestones Reached
Winter 2003 - Purchase of prime property at the intersection of Winton & Westfall Roads, totaling 161 acres owned.
Winter 2006 - Favorable settlement of eminent domain dispute with the Town of Brighton.
January 2007 - Sold 71 acres of appreciated property to the Town of Brighton
2007-2009 - Began the architectural design process, and gathered the right team of builders and advisors
November 2009 - DEIS (Environmental Impact Study) approved by Town of Brighton
November 2009 - Building Your Future Campaign launched to raise funds for construction of Phase One building.
What We've Accomplished Since 2004
Traffic Studies and Impact
Parking Studies and Impact
Stormwater Management Studies and Impact
Views and Vistas Studies and Impact
Police, Fire, Emergency Studies and Impacts
Ecology and Wildlife Studies and Impact
Land Use Studies and Impacts
Utility Studies and Impacts: water, sewer, gas, electric
School Impacts
Tax and Financial Impacts
Construction Impacts
Had 2 Neighborhood meetings
Numerous meetings with Town Staff
Made 12 separate Submissions and Applications
Had 7 official Sketch Concept Plan meetings
Had 1 Public HearingMade numerous presentations
Hired Architects
Hired 2 Civil Engineering Firms
Met with Town Board
Many meetings with Planning Board
Met with Architectural Review Board Hired Builder
Hired Developer
Next Steps
1 more Public Hearing
8 more Submissions and Applications
7 more Meetings
Detailed Architectural, Engineer, and Construction documents for next 6-10 months
Groundbreaking expected by the end of 2010

How to Give to the Building Your Future Campaign